Administratief Akkoord tussen het Koninkrijk der Nederlanden en Bangladesh inzake het project " Integrated Planning for Sustinable Water Management (IPSWAM)"

Administrative Arrangement

The Netherlands Minister for Development Co-operation, being the competent Netherlands Authority for the purpose of this Administrative Arrangement, hereinafter referred to as ``the Netherlands Party", represented in this matter by Sjef IJzermans, Ambassador of the Kingdom of the Netherlands to Bangladesh,

and

The Economic Relations Division of the Ministry of Finance, Government of the People's Republic of Bangladesh, being the competent Bangladesh Authority for the purpose of this Administrative Arrangement, hereinafter referred to as ``the Bangladesh Party",

Having regard to the provisions of Article I of the Agreement on Technical Co-operation between the Kingdom of the Netherlands and the People's Republic of Bangladesh signed at Dhaka on 19 May 1977, hereinafter referred to as ``the Agreement",

Have entered into the following administrative arrangement:

Article

I

The Project

Article

II

The contribution by the Netherlands Party

The Netherlands Party shall make a total maximum contribution to the project of EUR 11,982,065. Of this contribution a maximum amount of EUR 7,236,180 will be made available as Technical Assistance through direct contracting by the Netherlands Party and a maximum amount of EUR 4,541,685 will be made available as Financial Assistance to the Bangladesh Water Development Board (BWDB). A maximum amount of EUR 204,200 will be available for a Joint Mid Term Review Mission and for Joint Annual Review Missions.

Article

III

The contribution by the Bangladesh Party

The Bangladesh Party shall make the contribution to the Project of Bangladesh Taka 252,500,000 in accordance with the Project Document referred to in Article VII, paragraph 1 of this Arrangement.

Article

IV

The Executive Authorities

Article

V

Delegation

Each of the Executive Authorities shall be entitled to delegate under its own responsibility, partly or entirely, its duties in connection with the Project to other authorities or organisations. In doing so, the Executive Authorities shall inform each other in writing of any such delegation and of the extent of the delegation.

Article

VI

The Team Leader

Article

VII

The Plan of Operations

Article

VIII

Status of the Netherlands Staff

The personnel supplied by the Netherlands Party shall enjoy the privileges and immunities, mentioned in the Articles II and III of the Agreement.

Article

IX

Equipment and Materials

Article

X

Reporting

The Team Leader shall, in close consultation with the Project Director, submit to both Executive Authorities a semi-annual report in English every six months on the progress made in the execution of the Project and on the expenditure incurred by both Executive Authorities. Approval or rejection of expenditures made from the Netherlands contribution is entirely and solely at the discretion of the Netherlands Executive Authority. On termination of the Project, the Team Leader shall submit to all parties involved in final report in English on all aspects of the work done in connection with the Project.

Article

XI

Evaluation

The Executive Authorities shall have the Project evaluated annually by a Joint Annual Review Mission. These missions will review the achievements of the past year, thoroughly appraise the Annual Plan of Operations for the coming year, and if necessary propose changes in project activities beyond the one-year period. In May 2005, the Executive Authorities shall have the Project evaluated by a Joint Mid Term Review Mission.

Article

XII

Settlement of disputes

Any dispute concerning the interpretation or implementation of this Administrative Arrangement which cannot be settled in consultation between both Parties shall be referred to the respective Governments.

Article

XIII

Entry into force and duration

This Administrative Arrangement shall enter into force on the date of signature by both Parties and shall expire at the end of the period mentioned in Article 1, paragraph 3, of this Arrangement or on the date on which the Project has been completed in conformity with the provisions of this Arrangement and of the Project Document, whichever date is the later.

DONE at Dhaka on 2 November 2003 in duplicate in the English language

For and on behalf of the Netherlands Minister for Development Co-operation

SJEF L. IJZERMANS

Sjef L. IJzermans

Ambassador Royal Netherlands Embassy in Dhaka

For and on behalf of the Economic Relations Division of the Ministry of Finance, Government of the People's Republic of Bangladesh

M. TASADDUQ HUSSAIN BEG

Mr. Mirza Tasadduq Hussain Beg

Secretary Economic Relations Division Ministry of Finance