Administratief Akkoord tussen het Koninkrijk der Nederlanden en Egypte inzake het project "Preparatory Activities Component - Integrated Irrigation Improvement and Management Project (PAC-IIIMP) or WaterBoards-IIIMP"

Administrative Arrangement

The Netherlands Minister for Development Cooperation, being the competent Netherlands Authority for the purpose of this Administrative Arrangement, hereinafter referred to as “the Netherlands Party”, represented in this matter by the Ambassador Extraordinary and Plenipotentiary of Her Majesty the Queen of the Netherlands in Cairo, Mr. T.F. de Zwaan,

and

the Ministry of Water Resources and Irrigation, represented in this matter by The Minister, Dr. Mahmoud Abu Zeid, being the competent Egyptian Authority for the purpose of this Administrative Arrangement, hereinafter referred to as the “Egyptian Party”,

Having decided to cooperate in the field of Integrated Water Management, specifically through the Integrated Irrigation Improvement and Management Project (IIIMP) with the World Bank (WB) and German Development Bank (KfW),

Having regard to the provisions of Article I of the Agreement concerning Technical Cooperation between the Kingdom of the Netherlands and the Arab Republic of Egypt signed in Cairo on October 30, 1976, hereinafter referred to as “the Agreement”,

Have agreed as follows:

Article

I

The Project

Article

II

The Netherlands Contribution

Article

III

The Egyptian Contribution

Article

IV

The Executive Authorities

Article

V

Delegation

Each of the Executive Authorities, mentioned in Article IV, shall be entitled to delegate under its own responsibility, partly or entirely, its duties in connection with the Project to a third party. In doing so, the Executive Authorities shall inform each other in writing of the names of the persons or institutions delegated and of the extent of the delegation.

Article

VI

The Consultant

The Netherlands Consultancy Office shall be responsible to the Netherlands Executive Authority for the correct implementation of the Netherlands contribution.

The Consultancy Office shall act in close consultation with the Egyptian Executive Authority and respect the operational instructions given by the said Authority to the Egyptian personnel. The Egyptian Executive Authority shall provide the Consultancy Office with any information that may be considered necessary by both parties for the execution of the Project and arrange meetings with local government and other authorities as necessary during the course of the Consultant’s work.

Article

VII

The Working Document

Article

VIII

Status of Netherlands Staff

The Netherlands staff to this Project shall enjoy the privileges and facilities mentioned in Articles II and III of the Agreement.

Article

IX

Status of the Netherlands Equipment and Materials

In conformity with the provisions of Article 5 of the Agreement, the Government of the Arab Republic of Egypt will exempt from all import duties and other charges the equipment (inclusive passenger cars, spare parts, etc.) and other supplies provided by the Netherlands Government in connection with the Project.

Upon completion of the project the ownership of the equipment and materials of the project shall be transferred to the Government of Egypt unless otherwise agreed between the Executive Authorities.

Article

X

Reporting

The Netherlands Consultant shall submit to both Executive Authorities the following reports (in English):

  • Inception Report, due on August 1st, 2006

  • Annual work Plan and budget, due every calendar year on 15th October

  • Semi-annual progress report (narrative and financial), due within two months after the end of the period

  • Final narrative and financial report over the project period May 1st, 2006 till April 30th, 2009, due on August 1st, 2009.

Article

XI

Evaluation

Article

XII

Settlement of Disputes

Any dispute arising out of the interpretation or implementation of this Administrative Arrangement which cannot be settled by consultations between the two Parties shall be referred to the respective Governments.

Article

XIII

Entry into Force and Duration

This Administrative Arrangement shall enter with retroactive effect to 1 May 2006. It shall expire either at the end of the period stated in Article I, paragraph 3, of this Arrangement or on the date on which the Project has been completed in conformity with the provisions of this Arrangement and of the Working Document, whichever date is the later.

DONE at Cairo on the 17th day of September 2006, in two originals in the English language.

For the Netherlands Minister for Development Cooperation,

T.F. DE ZWAAN

Ambassador

For the Egyptian Minister of Water Resources and Irrigation,

MAHMOUD ABU. ZEID

Minister of Water Resources and Irrigation