Administratief Akkoord tussen het Koninkrijk der Nederlanden en Egypte inzake het project "Fayoum Water Users Organisation Project"

Administrative Arrangement

The Minister for Development Cooperation of the Kingdom of the Netherlands, being the competent Netherlands Authority for the purpose of this Administrative Arrangement, hereinafter referred to as “the Netherlands Party”, represented in this matter by the Ambassador Extraordinary and Plenipotentiary of Her Majesty the Queen of the Netherlands in Cairo,

and

the Minister of Water Resources and Irrigation of the Arab Republic of Egypt being the competent Egyptian Authority for the purpose of this Administrative Arrangement, hereinafter referred to as the “the Egyptian party”;

Having decided to cooperate in the field of “Water Management in Fayoum”

Having regard to the provision of Article I of the Agreement on Technical Cooperation between the Kingdom of the Netherlands and the Arab Republic of Egypt, signed in Cairo on 30 October 1976, hereinafter referred to as the Agreement”,

Have entered into the following administrative arrangement:

Article

I

The Project

Article

II

The Netherlands Contribution

Article

III

The Egyptian Contribution

Article

IV

The Executive Authorities

Article

V

Delegation

Each of the Executive Authorities, mentioned in Article IV, shall be entitled to delegate under its own responsibility, partly or entirely, its duties in connection with the Project to a third party. In doing so, the Executive Authorities shall inform each other immediately in writing of the names of persons or institutions delegated and of the extent of such delegation.

Article

VI

The Team leader

The Team leader shall be responsible to the Netherlands Executive Authority for the correct implementation of the technical assistance component. The Team leader shall act in close consultation with the Egyptian Executive Authority and respect the operational instructions given by the said Authority to the Egyptian personnel. The Egyptian Executive Authority shall provide the Team leader with any information that may be considered necessary by both parties for the execution of the Project.

The Team leader, who will also be a member of the Advisory Committee shall work in close consultation with the said committee and respect its recommendations.

Article

VIII

The Schedule of Operations

Article

VIII

Reporting

The Team leader shall submit six-monthly reports in the English language on the progress made in the execution of the Project to both Executive Authorities. Narrative and financial reporting will reflect on activities implemented with the Netherlands and Egyptian contributions. At the termination of the Project, the Team leader shall submit a final report in the English language on all aspects of the work done in connection with the Project to all parties involved.

Concerning the “Contribution Arrangements”, the MWRI shall present, in English, to the Embassy of the Kingdom of the Netherlands, six-monthly progress and financial reports and claims and a final report at the end of the Project.

Article

IX

Status of the Netherlands Staff

The non-Egyptian staff assigned to the Project by the Netherlands shall enjoy the privileges and facilities, as described in the Articles II and III of the Agreement.

Article

X

Status of Netherlands Equipment and Materials

Article

XI

Evaluation

The Executive Authorities may start an evaluation of the Project during the last year of the Project.

Article

XII

Settlement of Disputes

Any disputes concerning the implementation of this Administrative Arrangement, which can not be settled in consultation between the two Parties, shall be referred to the respective Governments and shall be settled in a way to be decided upon by the latter.

Article

XIII

Entry into Force and Duration

This Administrative Arrangement shall enter into force with retroactive effect to 1 January 2007 on the day of signature by both Parties and shall expire at the end of the period mentioned in Article I, paragraph 3, of this Arrangement or on the date on which the Project has been completed in conformity with the provisions of the Arrangement and the Schedule of Operations, whichever date is the later.

DONE in Cairo on the 12th of April 2007, in two originals in the English language.

For the Minister for Development Cooperation of the Kingdom of The Netherlands,

T.F. DE ZWAAN

Ambassador

The Minister of Water Resources and Irrigation of the Arab Republic of Egypt,

MAHMOUD ABU. ZEID